2023
RE-ACTIVATION
Bolt 20E replacement for BOP
2023
Rope Access
Disconnecting the GOOSE NECK HOSE
2015
commissioning
Connecting the MLO Piping to the HP Compressor
2023
RE-ACTIVATION
Installation procedure for the DIVERTER pressure test
2017
Punch Work
The oil seal was replaced after decomposition due to leakage.
2017
commissioning
Check the fluid mixing system
2017
Punch Work
Quick connector replacement operation
2023
Rope Access
Hydro hose replacement operation
2017
commissioning
Move operation for BOP inspection
2023
Modification
BOP KILL PIPE CORRECTION INSTALLATION WORK
2017
Preservation & Maintenance
Cleaning and replacing the HPTU filter
2023
Preservation & Maintenance
Ram Block rust prevention work
2017
Preservation & Maintenance
Preservation & Maintenance
2023
commissioning
commissioning of loading arm
2023
Punch Work
Check and replace the Diverter valve seal